Short answer
Site prep is the dirt work that gets raw ground ready for a foundation. In order, it is land clearing, light demolition, cut and fill, rough grading, building pads and finish grading. Each step has a local rule. In Vancouver, moving more than 10 cubic yards of earth usually needs a grading permit.
What are the steps of site prep, in order?
There are six steps, and they run in the order the work happens. This is the scope listed on our site prep and grading page:
- Land clearing. Trees, brush and stumps come out and the site is opened up.
- Light demolition. Old structures and slabs are taken out of the way.
- Cut and fill. Dirt is moved to where the plans need it.
- Rough grading. The site is shaped to the grading plan.
- Building pads. Pads are cut to elevation for the next trade.
- Finish grading. Final grades are set so the lot drains right.
You may also see this called pre-construction site clearing or site preparation services. Not every lot needs every step.
Each step below has a rule attached. These are the rules as of November 2026. Codes change, so confirm with the permit office for your address. The City of Vancouver, Clark County and each smaller city run their own permits.
What happens during land clearing?
Clearing removes the trees, brush, stumps and roots from the area you will build on. It is the first step because nothing else can be measured or graded until the ground is open.
Two rules touch clearing before a saw starts:
- Trees. Inside Vancouver, city code requires a tree removal permit for most trees. On a lot with one home, trees under 12 inches across the trunk are usually exempt. In unincorporated Clark County, clearing timber to build falls under county forest practice rules. See do I need a permit to remove trees.
- Debris. Burning land clearing debris is banned inside city limits and urban growth areas. Debris gets chipped, ground or hauled. See can I burn land clearing debris.
What counts as light demolition?
Light demolition is removing what is in the way, such as an old shed, a garage or a concrete slab. It happens early, so the grading crew has a clean site.
The rules here have a clock on them. The Southwest Clean Air Agency requires an asbestos inspection before any demolition. Then you file a notice and wait 10 days. The city or county may also require a demolition permit. Start this paperwork early, since the wait cannot be skipped. See do I need a permit to tear down a garage or shed.
What are cut and fill?
Cut is dirt taken away from a high spot. Fill is dirt placed in a low spot. Together they turn a sloped or lumpy lot into the shape on the plans.
When the cut and the fill are close to equal, the dirt stays on the lot. When they are not, dirt gets trucked in or out. Ask for both totals in cubic yards. A cubic yard is a block of dirt three feet on each side.
This is the step that triggers a grading permit, and Vancouver sets a low line. The city’s Grading Projects FAQ says one is required for nearly all projects that disturb or move more than 10 cubic yards of earth or vegetation. A house foundation dig can skip the separate permit only under a short list of conditions.
Outside city limits, Clark County Code 14.07 sets the line by lot type. On an urban area site under one acre, a grading permit is required when grading involves more than 50 cubic yards. Any site in a critical area has the same 50 cubic yard line. For the full rules, see do I need a grading permit in Vancouver.
Before any digging, underground utilities must be located. Under RCW 19.122.030, the excavator must request locates at least two full business days before digging. The request can be made no more than 10 business days ahead. The excavator also marks the dig area in white. The excavator makes the call, so on an LPG job that responsibility is ours. Private lines past the meter usually are not marked. See does 811 mark private lines.
What is rough grading?
Rough grading shapes the whole site to the grading plan. The plan shows the height the ground should be at each point. After rough grading, the driveway, the yard slopes and the house area are all close to their planned heights.
Open dirt is where erosion rules bite. Rain on bare soil carries mud into streets and storm drains. Both the city and the county require erosion controls on sites with disturbed ground. Larger sites also need a state permit. The Washington Department of Ecology’s Construction Stormwater General Permit covers sites that disturb one acre or more when runoff could leave the site. See erosion control rules in Clark County for what must be in place and when.
What is a building pad?
A building pad is the flat, firm area of ground where the house foundation will sit. It is cut or filled to an exact height, called the pad elevation, taken from the plans.
A pad has three jobs:
- Right height. The pad sets how high the house sits. That affects the driveway slope, the sewer connection and how water drains.
- Right size. The pad covers the footprint of the house, with room for the foundation crew to work.
- Firm soil. The ground must be solid enough to carry the house. Soft or loose soil is removed or packed down in layers. Packing soil down is called compaction.
If the pad is built on fill, the fill may need to be tested. See compaction testing and who pays. Ask who is responsible for the pad elevation and how it will be checked before the foundation crew arrives.
What is finish grading?
Finish grading sets the final shape of the ground after the house is built. The goal is ground that slopes away from the foundation, so water runs off and does not pool against the house.
Finish grading comes last because foundation work, utility trenches and backfill all disturb the lot again. It leaves the lot ready for topsoil, lawn and planting.
What is not part of site prep?
Site prep stops at the ground. The foundation, the concrete and the framing belong to other trades. Utility lines are often done by the same excavation contractor, but they are their own scope. Permits, surveys and soil reports are usually the owner’s or builder’s job unless the bid says otherwise.
That is why the bid matters. A site prep bid should list each step it includes and each thing it leaves out.
Do this now
- Find out who governs your address: City of Vancouver, Clark County or another city.
- Walk the lot and list the trees, old structures and slabs that are in the way.
- Ask your designer or builder for the cut and fill totals in cubic yards.
- Call the permit office and ask which permits the clearing, demolition and grading need.
- Ask each bidder to list which of the six steps are included, and who gets each permit.
More questions
How is a building pad different from a foundation?
The pad is shaped and packed ground. The foundation is the concrete that sits on it.
Can clearing and grading start before the building permit is issued?
It depends on the permits in hand. See can I clear and grade before my building permit.
Sources
- City of Vancouver: Grading Projects FAQ (read November 23, 2026)
- Clark County Code 14.07: Grading, Excavation, Fill, and Stockpile (read November 23, 2026)
- Revised Code of Washington 19.122.030: Excavator and facility operator duties before excavation (read November 23, 2026)
- Washington Department of Ecology: Construction Stormwater General Permit (read November 23, 2026)
Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.