Do I Need a Permit to Tear Down a Garage or Shed?

Updated For homeowners and builders5 minute read

Short answer

Usually yes. In Vancouver, any building that is occupied or has a utility connection needs its own demolition permit. Clark County requires one to remove any structure that was permitted, including a detached garage. Before any demolition, the clean air agency requires an asbestos inspection and a notice, then a 10 day wait.

When does Vancouver require a demolition permit?

Inside Vancouver city limits, each building that is occupied or has any utility connection needs a separate demolition permit. The city calls it a DMO permit. Its Demolition Projects FAQ names electrical, gas, water and sewer as the connections that count.

So a detached garage with power run to it needs its own permit. The FAQ treats small sheds differently. Small unoccupied accessory structures, such as sheds without utilities, can go on one application with the main building.

The FAQ does not say what happens when a shed with no utilities is the only thing coming down. Ask the Permit Center before you start. These are the rules as of November 2026. Codes change, so confirm with the permit office for your address.

The city FAQ adds a few more rules:

  • If the building is more than 50 years old, you submit photos of every side of it.
  • All holes must be filled, and the site graded back to a natural grade.
  • Removing a septic system needs its own demolition permit.

What does Clark County require outside city limits?

In unincorporated Clark County, a demolition permit applies to removing any structure or accessory use that was previously permitted. The county’s residential permits page calls it a DEM permit. Its examples include a house, an attached or detached garage, a shop, a pool, a deck and a patio cover.

The same page says sheds of 200 square feet or less do not need a building permit to build. It does not say whether tearing one down needs a demolition permit. Ask the county Permit Center, and tell them the size and whether it has power or water.

Manufactured and mobile homes are different. The county sends those to the Washington Department of Labor and Industries.

Camas, Washougal, Battle Ground, Ridgefield and La Center issue their own demolition permits. Call that city’s permit office.

Do I need an asbestos inspection for a garage or shed?

Yes, for any demolition, and it must be done by a certified inspector. This rule comes from the Southwest Clean Air Agency, called SWCAA. It is separate from the city or county permit, and it covers all of Clark County.

SWCAA Regulation 476 took effect in its current form on March 22, 2026. It says the owner must get an asbestos inspection before any demolition project. The inspector must be an AHERA accredited building inspector. AHERA is the federal training standard for asbestos inspectors.

The rule’s definition of a structure lists houses, garages, pole buildings, canopies and lean-tos. It leaves out wood decks and fences. A small shed is not named either way, so call SWCAA at 360-574-3058 and ask.

Old garages can hold asbestos in places you would not expect. The rule lists roofing, cement siding, flooring, mastics and wall textures as suspect materials, no matter what year they went in.

Can I skip the inspection if I own the home and live in it?

No, not for demolition. The owner exception in the rule only covers renovation work. An owner who lives in a single family home may handle their own renovation without a certified inspector. The rule then says an asbestos inspection is required when a demolition project is planned.

Owner occupants do get one break. If the inspection finds asbestos, an owner who lives in the home may remove it themselves. They must give SWCAA notice first and follow the handling rules. Everyone else must hire a certified asbestos contractor.

How long is the wait before demolition can start?

The wait is 10 days after SWCAA receives your complete notice and fee. You file a Notice of Demolition with a copy of the inspection report. The rule requires this notice even when the inspection finds no asbestos at all.

Work may start the day after the 10 day period ends. The project must also start on the date shown on the notice. If your date changes, tell SWCAA before the original date.

The SWCAA fee schedule, effective January 9, 2026, lists $77 per demolition notice without asbestos. If asbestos is present, the normal asbestos removal fee is added. All asbestos found must be removed before the structure comes down.

Keep the inspection report at the site. The rule says it must be available to SWCAA and to everyone working there.

What about power, gas, water and sewer?

Every utility has to be shut off and disconnected before the structure comes down. That is basic safety, and the utility connections are also what trigger the Vancouver permit. Call each provider early, since each one schedules its own disconnect.

Sewer and septic get extra attention. The Vancouver demolition application asks whether the building is on sewer or septic and whether the water supply will be abandoned. How a sewer line must be capped depends on your sewer provider. No single published capping rule covers every address, so ask the permit office and your sewer provider.

Pulling out a slab or footings means digging. Washington law requires a utility locate request through 811 before any excavation. See does 811 mark private lines for what gets marked and what does not.

What happens to the debris and the ground afterward?

Demolition debris must be hauled to a proper disposal site. It cannot be burned. See can I burn land clearing debris for the burning rules.

Our site prep and grading page lists light demolition as old structures and slabs taken out of the way. With any contractor, ask who gets the demolition permit, who orders the asbestos inspection, and who files the SWCAA notice. Get the answers in the bid. For how demolition fits with clearing and grading, see what site prep includes.

Oregon and Portland have their own demolition rules. This article covers Clark County, Washington only.

Do this now

  1. Find out who governs your address: City of Vancouver, Clark County or another city.
  2. Write down the structure’s size, age and every utility that runs to it.
  3. Call that permit office and ask if your garage or shed needs a demolition permit.
  4. Hire an AHERA accredited building inspector for the asbestos inspection. SWCAA keeps a list of inspectors on its website.
  5. File the Notice of Demolition with SWCAA, then count 10 days before any work starts.

More questions

Does a shed with no power or water need a demolition permit in Vancouver?

The city FAQ lets small unoccupied sheds without utilities ride on the main building’s application. It does not cover a shed removed by itself, so ask the Permit Center.

How long should I keep the asbestos report?

SWCAA requires the owner to keep the full inspection report for at least 24 months.

Is taking out an old concrete slab demolition?

A slab by itself is not a building, but breaking it out is still digging. Request utility locates first, and ask the permit office if a grading permit applies.

Sources

Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.