Short answer
On a home site in Clark County or Vancouver, the contract decides who installs erosion control, but the law holds the owner responsible too. County code makes it a joint duty of the owner and whoever disturbs the soil. Controls go in before work starts and must be inspected every week.
Who is legally responsible for erosion control?
The owner and the people doing the work are responsible together. As of November 2026, both local codes say so. Confirm the rules for your address with your permit office.
In unincorporated Clark County, the rule is in Clark County Code 40.386.010. The county updated it in 2026, and the adopted ordinance has the current text. It calls erosion control the “joint and severable responsibility” of the site owner and the person doing the land-disturbing work. That includes the permit applicant.
Inside the City of Vancouver, VMC 14.24.050 names four parties: the property owner, the person doing the work, the general contractor and the permit holder.
So hiring a contractor does not take the owner off the hook. If mud leaves the site, the city or county can come to either of you.
Camas, Washougal, Battle Ground, Ridgefield and La Center each run their own permits. Ask that city what it requires.
What has to be on a small home site?
Erosion controls have to be in place before any soil is moved. Clark County’s erosion control page lists the basics for every site:
- Controls go in before work begins and stay for the whole job.
- The construction access is covered with gravel.
- Neighbors, storm drains, wetlands and water bodies are protected before work begins.
- Controls are inspected every week and fixed when needed.
On a house lot, that most often means these items:
- Silt fence. A fabric fence along the low side of the lot. It slows muddy water so the dirt drops out.
- Stabilized construction entrance. A pad of rock where trucks leave the site. It knocks mud off the tires.
- Inlet protection. A filter at the nearest street storm drain.
- Cover. Straw, plastic, seed or erosion blankets over bare soil and dirt piles.
The county says to disturb no more ground than the job needs. Less bare soil means less to protect.
How fast does bare soil need cover?
Within two days in the wet season. The county page and Vancouver’s code, VMC 14.24.060, use the same limits:
- October 1 to April 30: soil cannot stay exposed more than two days.
- May 1 to September 30: soil cannot stay exposed more than seven days.
Winter work brings other limits too. See excavating in the rainy season.
Who cleans up mud on the street?
Whoever tracked it out has to clean it up that day. In Vancouver, the code says roads and paved surfaces must be cleaned at the end of each workday, or more often if needed. The mud is removed by shoveling and sweeping.
Hosing mud down the street is not allowed in the city unless the director approves it. Even then, the sediment has to be removed first. Wash water runs to the storm drain, and that is what the rule is trying to stop.
The county page says the same thing in fewer words. Shovel or sweep soil off roads and sidewalks.
Who inspects, and how often?
Someone on your side inspects every week, and the agency inspects too.
In unincorporated Clark County:
- A signed erosion control agreement is required before a building permit is issued.
- A licensed contractor must provide a certified erosion control person. A homeowner can do the erosion control work without one.
- Inspections happen weekly and are written in an erosion control log kept on site.
- The county’s Erosion Control Plan form says the named inspector must be on site or on call at all times.
In the City of Vancouver:
- A site erosion control inspection must be scheduled and approved before land-disturbing work starts.
- The site must be inspected at least once a week and after each rainfall.
- A maintenance log is kept on site.
- The work must be supervised by someone with formal erosion control training. A homeowner acting as their own contractor on their own property is exempt from that training rule.
The trained person is often called a CESCL. That stands for Certified Erosion and Sediment Control Lead.
What happens if the controls fail?
The agency can order more controls or stop the job. The county’s Erosion Control Plan form says failure to comply may bring a stop work order and enforcement action. In Vancouver, the director must require more controls if sediment reaches a water body, a neighbor or the street.
The job is also not over when the dirt work ends. Vancouver’s code says temporary controls come out within 30 days after the site is finally stabilized.
What should I ask so it is in the bid?
Ask who does each task, and get the answer in writing. Erosion control starts during site prep and grading, but it has to last until the yard is finished. Several trades will cross that silt fence.
Good questions for every bidder:
- Is erosion control a line item in your bid? What does it include?
- Who is the named inspector or CESCL for my site?
- Who does the weekly inspections and keeps the log?
- Who sweeps the street, and how often?
- Who maintains the controls after your crew leaves?
- Who takes the controls out at the end?
A new house may also need a stormwater plan for the roof and driveway. See does a new house need a stormwater plan. A site of one acre or more may also need a state stormwater permit from the Department of Ecology.
Do this now
- Find out who issues your permit: the City of Vancouver, Clark County or another city.
- Read the county’s erosion control page or VMC 14.24.060. Each takes about five minutes.
- Ask every bidder the six questions above and compare the answers.
- Write the inspector’s name and phone number where you can find them in a storm.
- Walk the low side of your lot after the first hard rain. Look for muddy water leaving the site.
More questions
Can a homeowner do their own erosion control?
Yes. Clark County says homeowners can perform the erosion control requirements themselves. Vancouver exempts a single-family homeowner acting as their own contractor from the training certificate. The other rules still apply.
Does a small project still need erosion control?
Yes. Clark County says all land-disturbing activities require a signed erosion control agreement before a building permit is issued.
Is there a state permit too?
Only for larger sites. The state permit applies when a site disturbs one acre or more, or is part of a larger plan that will.
Sources
- Clark County Community Development: Erosion control (read November 23, 2026)
- Clark County: Ordinance amending CCC 40.386, Stormwater and Erosion Control, effective July 1, 2026 (read November 23, 2026)
- City of Vancouver: VMC 14.24.050, Persons responsible for compliance (read November 23, 2026)
- City of Vancouver: VMC 14.24.060, Specific compliance requirements (read November 23, 2026)
Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.