Before You Dig · Slopes, soil & drainage

Do I Need a Soils Report Before Excavation?

Updated For homeowners and builders5 minute read

Short answer

Not always. A soils report, also called a geotechnical report, is required when the site calls for it. Clark County lists triggers such as a mapped landslide area, steep slopes, deep backfill and over-excavated lots. Vancouver requires engineering for retaining walls over 4 feet. The owner hires the engineer, not the excavator.

When is a soils report required in Clark County?

Clark County requires a geotechnical report when certain site conditions exist. A geotechnical report is a soils study by an engineer who tests the ground under your project.

The county posts its list on the Soil Investigations and Geotechnical Reports page, as of November 2026. The county calls these the minimum rules in the building code it has adopted. Codes change, so confirm with the Clark County Permit Center.

These triggers from the list come up most on home sites:

  • The strength or type of the soil is in doubt.
  • The soil is expansive clay.
  • The site is in a mapped landslide area.
  • The site has steep slopes and you want smaller setbacks than the code gives.
  • The backfill area is deeper than the depth of the footing bearing.
  • The lowest floor sits below the ground next to the foundation.
  • Digging is planned near existing foundations.
  • The lot has been over-excavated, which means dug deeper than planned.
  • The project is a subdivision.
  • The Chief Building Official requires one.

The county also says the report must be for your site. A report for a nearby lot or a similar project cannot stand in for it.

What does the City of Vancouver say?

Vancouver says a soils report may be required, based on the site. The city’s Prepare Your Plans overview names four things that can trigger one. They are site location, soil conditions, the presence of fill and tree removal.

The same page lists work that needs engineering. One item is retaining walls over 4 feet tall or walls that carry a surcharge. A surcharge is extra load on top, like a driveway or a slope.

Hazard areas add their own report. In Vancouver, a project in a possible geologic hazard area needs a critical areas report. Our article on building on a steep lot covers those rules for the city and the county.

Camas, Washougal, Battle Ground, Ridgefield and La Center each run their own permits. Ask that city what it wants.

Does every new house need one?

No. For a house, the residential code leaves the call to the building official. Washington has adopted the 2021 International Residential Code with state changes.

Section R401.4 of the Washington State Residential Code covers soil tests. Where data points to expansive, compressible, shifting or other questionable soil, the official decides whether to require a test.

Without a full study, the code lets the designer assume set bearing values. Bearing value is how much weight the soil can carry. For clay and silt soils, the table value is 1,500 pounds per square foot.

So a flat lot with known, firm soil may not need a report. A lot with fill, a slope, soft ground or a tall wall likely will. Ask the permit office before you finish your plans.

Who orders the report, me or the excavator?

The owner or the builder orders it. The county’s rules are written for geotechnical engineers who are hired by permit applicants. The excavator does not write the report.

The engineer must be a licensed civil Professional Engineer in Washington with geotechnical experience. That comes from the county’s page on geotechnical engineer responsibility.

The report goes in with the permit application. That means you need it early, before the plans are final.

What is in a soils report?

A soils report says what is under the ground and how to build on it. The engineer digs test pits or drills borings, tests samples and writes it up.

Clark County’s guide lists what a report covers. The main parts are:

  • A site plan that shows where the borings and test pits were dug.
  • The soil layers found and the groundwater level, if water was hit.
  • The foundation type, the bearing value and the expected settlement.
  • Slope stability, where there is a slope.
  • Temporary excavation and shoring advice.
  • Grading and earthwork notes, with compaction needs and fill specs.
  • Wet weather limits.
  • Drainage, both temporary and permanent.
  • Erosion control.

In landslide-prone areas the county asks for more. The engineer names the most stable part of the site and the best spot for the house. The report also sets the limits of the grading area.

The county guide adds a wet season rule for those areas. In general, no excavation is permitted there in the wet winter months. Digging between November 1 and March 31 needs extra analysis and the Building Official’s approval.

How does the excavator use the report?

The excavator uses it as the instructions for the dirt work. It tells the crew how deep to dig and how steep a cut can stand. It also says what fill to use and how tight to pack it.

That makes it a bid document too. Give every bidder the same report. Then ask each one if the price follows it, and get the answer in the bid. Our guide to comparing excavation bids shows what else to line up.

The engineer may come back during the job. The county can require the geotechnical engineer to monitor the site during construction. When it does, the engineer’s stamped final report must be accepted before the county approves occupancy.

Soil testing during the work is a related cost. See who pays for compaction testing. We do the excavation on custom home sites, including foundations and basements on sloped and tight sites.

Do this now

  1. Look up the lot on Clark County MapsOnline and check the slope, hazard and soil layers.
  2. Ask the seller or the past owner for any soils report done for that exact lot.
  3. Call the permit office for your address and ask if your project needs a geotechnical report.
  4. If it does, hire a Washington licensed geotechnical engineer before your plans are final.
  5. Give the finished report to every excavator who bids the job.

More questions

Can I use a soils report from the lot next door?

No. Clark County says the report must be specific to the project site. A report for a nearby site or a similar project cannot be used in its place.

Does my excavator do the soils report?

No. A licensed geotechnical engineer does it, hired by the owner or the builder. The excavator follows the report.

Is a soils report the same as compaction testing?

No. The report comes before the work and sets the rules. Compaction testing happens during the work and checks that fill was packed to those rules.

Sources

Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.

→Start a project

Have a site to talk through?

Send the address and what you want built. We’ll look at it and tell you what the dirt work involves.