Before You Dig · Bids & hiring

Why Are My Excavation Bids So Far Apart?

Updated For homeowners and builders5 minute read

Short answer

Bids are far apart because each contractor priced a different job. One bid includes haul-off, rock and erosion control. Another leaves them out. Line the bids up item by item before you look at price. In Washington, a contractor must also give you a written disclosure statement on home jobs of $1,000 or more.

Why would two contractors price the same lot so differently?

They did not price the same work. Each one read your plans, walked your lot, and made guesses about what you want and what is in the ground. Those guesses are called the scope. The scope is the list of what the price covers.

A low bid often has a short scope. A high bid often has a long one. You cannot tell which bid is the better deal until both cover the same list.

Which line items have to match?

Every item below should show up in every bid, as included or as left out. Make a list and check each bid against it.

  • Clearing and stumps. Are trees, brush and stumps removed? Are the stumps hauled away or left in a pile?
  • Export and haul-off. Is extra dirt trucked off the lot? How much dirt did they plan for?
  • Dump fees. Who pays the fee where the dirt, stumps or debris get dumped?
  • Imported rock and fill. How much crushed rock or fill dirt is in the price, and for which areas?
  • Erosion control. Are silt fence, a rock entrance and other mud controls included? Who keeps them up?
  • Compaction. Will fill be packed down in layers? Is testing in the price or paid by you?
  • Utilities. Which trenches and pipes are covered: water, sewer, storm, power, gas? From where to where?
  • Permits. Who applies and who pays? Your permit office is the City of Vancouver, Clark County or your own city.
  • Rock and bad soil. What happens if they hit hard rock, soft mud or water? At what rate?
  • Final grade. Does the price stop at rough grade, or does it include the smooth final shaping?
  • Cleanup. Are the street, the driveway and the neighbor’s side left clean at the end?

What is an exclusion, and why does it matter?

An exclusion is work the bid says it does not cover. Look for the words “excluded,” “by owner,” or “not included.” A good bid lists them in plain view.

An exclusion is not a trick. It tells you what you still have to pay for. The trouble comes when one bid lists its exclusions and another bid just says nothing. Silence is not a yes. If an item is not written in the bid, ask, and get the answer in writing.

What does Washington say a bid and contract should have?

Washington L&I tells owners to get bids in writing and to compare more than price. Its Hire Smart guide says to look at the scope of work, warranties, references and completion dates. It also says to check that permit fees, taxes and other costs are in the bid. This is as of November 2026, so confirm with L&I.

L&I says every contract should list, at a minimum:

  • The price, with sales tax.
  • The payment terms and the completion date.
  • Permit fees, if they apply.
  • The specific work to be done.
  • The materials, major suppliers and subcontractors.
  • Warranties and how change orders work.

A change order is a written change to the job or the price after you sign. Dirt work has more surprises than most trades. Read what happens if the excavator hits rock or water before you pick a bid.

What paperwork does the contractor have to give me?

The contractor must give you a written disclosure statement before work starts. RCW 18.27.114 requires it for work on four or fewer homes when the bid is $1,000 or more. It is also required on a commercial building when the bid is $1,000 or more but less than $60,000.

The notice gives the contractor’s registration number and bond amount. It warns that the bond might not be enough to cover a claim. It also tells you about liens.

A lien is a claim on your property for an unpaid bill. If your contractor does not pay a supplier or a sub, that company can lien your land. L&I’s lien page says a lien must be filed within 90 days of the work stopping or the materials arriving. The state notice says you could pay twice for the same work.

You have two tools. The notice says you may hold back a set percent of the contract for a stated time. L&I says to ask for a signed lien release from major subs and suppliers before your final payment.

Is the lowest bid a bad bid?

No, not by itself. A low bid can be a fair price from a crew that is close by or has an opening. It can also be a bid that left things out. L&I warns that focusing only on price may get you a poor result.

Ask each bidder how much dirt, rock and trucking they figured. If one planned to haul far less dirt than the others, find out why before you sign.

Also check that each bidder is registered. Here is how to check an excavation contractor’s license. Our residential excavation page lists the steps in a home dig, from clearing to final grade. It can help you build your list.

Do this now

  1. Write one scope sheet for your job using the eleven items above. Send the same sheet to every bidder.
  2. Ask each bidder to mark every item as included, excluded or by owner, in writing.
  3. Put the bids side by side and circle every blank. Ask about each one.
  4. Look up each bidder on L&I’s Verify tool before you compare price.
  5. Ask how extra work is priced, and get that in the bid too.

More questions

How many bids should I get?

L&I does not give a number. It says to interview several qualified, registered contractors and get the bids in writing.

Should permit fees be in the bid?

The bid should say so one way or the other. L&I tells owners to check that permit fees, taxes and other costs are included.

Can my land be liened if I paid my contractor in full?

Yes. L&I says you have the final responsibility to see that subs and suppliers were paid, even if you paid your contractor in full.

Sources

Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.

→Start a project

Have a site to talk through?

Send the address and what you want built. We’ll look at it and tell you what the dirt work involves.