Short answer
The job stops being the job that was bid. Who pays depends on what your contract says about hidden conditions, so settle it before the dig. Washington L&I tells owners to agree in writing, before work begins, on how cost overruns are handled, and to get every change in writing. This applies to any owner or builder.
Why can’t the contractor know what is down there?
Nobody can see under the ground before it is opened. A bid is built from what shows on top, from your plans, and from a soils report if you have one. The rest is a guess.
Three things cause most of the surprises. One is rock that a bucket cannot dig. One is groundwater that fills the hole. One is soft or wet soil that cannot hold up a house, often called unsuitable soil. Old buried fill, stumps and trash come up too.
Who pays for the rock or the water?
Your contract decides. If the contract says nothing, you and the contractor will argue about it with the hole open and the crew standing by. That is the worst time to set a price.
So the real question is how your bid is priced. There are three common ways, and each one puts the risk in a different place.
What is the difference between lump sum, unit price, and time and materials?
They are three ways to set the price, and they split the risk in three ways.
- Lump sum. One fixed price for a written scope. The contractor carries the risk for what is in the scope. Read the fine print. Many lump sum bids exclude rock, water and bad soil.
- Unit price. A set price for each unit of work, like each cubic yard of rock dug or each ton of rock brought in. You pay for the amount that is really done. You carry the risk on how much, but the rate is fixed.
- Time and materials. You pay by the hour for crew and machines, plus the materials. You carry the most risk. The bill grows with every hour.
A fair setup for a home site is often a mix. The known work gets a lump sum. The unknowns get unit prices that are written in the bid before anyone digs.
What is an allowance?
An allowance is a set amount in the bid for work nobody can measure yet. For example, a bid might carry a stated amount of soft soil to dig out and replace with rock.
If the real amount is less, you should get money back. If it is more, you pay more at the stated rate. An allowance is only useful when it names the amount, the unit and the rate. Ask for all three.
What should a change order say before extra work starts?
A change order is a written change to the job or the price after you sign. It should be signed before the extra work is done, not after.
L&I’s Hire Smart guide says to get any change in material or scope in writing and to avoid verbal contracts or amendments. It also says to agree with your contractor on how cost overruns will be handled before work begins, and to write that down. This is as of November 2026, so confirm with L&I.
A good change order answers five things:
- What was found, and where. Photos help.
- What extra work will be done.
- The price, or the rate and a cap.
- How many days it adds.
- Who signed it, and the date.
Does a soils report take the risk away?
No. It lowers the risk, but it does not remove it. A soils report comes from a geotechnical engineer, an engineer who studies the ground. The engineer digs test pits or drills holes at a few spots and writes up what is there.
The report can tell bidders how deep the firm soil is and if water showed up in the holes. That gives everyone the same facts to bid from. But the ground between the test holes can be different. A report done in a dry August may not show the water that is there in January. Groundwater is higher in the wet months.
If you have a report, give it to every bidder. Then ask each one to say in writing that the price is based on it. More on this in do I need a geotech report before excavation.
You can also look at the federal soil map for free. The USDA’s Web Soil Survey has soil maps and data for most counties. The site itself says an onsite investigation is needed in some cases. Use it as a first look, not a final answer.
Why does water stop the work?
Water stops the work because it is a safety rule, not just a mess. Washington’s excavation rule, WAC 296-155-655, says workers must not work in a hole where water has built up or is building up. The rule allows it only when steps are taken to protect them.
Those steps can be pumps, trench shields or other gear. If pumps are used, the rule says a trained person must watch them. All of that costs time and money. A bid should say who pays for pumping and for how long.
Ask where the pumped water will go, too, and get the answer in the bid. Our article on working in the rainy season covers wet weather digs.
Sites where accuracy matters most are the ones where these terms matter most. See our custom home excavation page for that kind of work.
Do this now
- Ask each bidder in writing: “What did you assume about rock, groundwater and soft soil?”
- Ask for unit prices in the bid for rock digging, soft soil dug out and replaced, and pumping water.
- Ask how the bid defines rock. Get the definition in writing.
- Put one line in the contract: no extra work starts without a signed change order.
- Give every bidder the same soils report, if you have one, and look up your lot on the Web Soil Survey.
More questions
What counts as rock?
It depends on your contract. Some bids call it rock only when a machine of a named size cannot dig it. Ask for the definition before you sign.
Should I hold back money for surprises?
Yes, plan for them. No one can give you an honest number without knowing your site, so ask each bidder what surprises they have seen near your lot.
Is a low lump sum bid safer than unit prices?
Not always. A lump sum that excludes rock, water and bad soil leaves those costs open. Unit prices at least fix the rate ahead of time.
Sources
- Washington L&I: Hire Smart Step-by-Step (read November 23, 2026)
- WAC 296-155-655: General protection requirements for excavations (read November 23, 2026)
- USDA Natural Resources Conservation Service: Web Soil Survey (read November 23, 2026)
Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.