Short answer
Usually, yes. This applies in unincorporated Clark County and the City of Vancouver. A project needs a stormwater plan when it adds or replaces 2,000 square feet or more of hard surface. Disturbing 7,000 square feet or more of land triggers it too. Roofs, driveways and patios all count as hard surface.
What size house triggers a stormwater plan?
The trigger is 2,000 square feet of hard surface or 7,000 square feet of disturbed land. As of November 2026, the Clark County Stormwater Manual sets these levels in Book 1:
- 2,000 square feet or more of new plus replaced hard surface, or 7,000 square feet or more of land disturbance. The project must meet Minimum Requirements 1 to 5.
- 5,000 square feet or more of new plus replaced hard surface. The project must meet Minimum Requirements 1 to 9. That is a bigger, engineered plan.
A house with a garage, a driveway and a patio can reach 2,000 square feet fast. Clearing and grading a lot can pass 7,000 square feet even when the house is small.
The county adopted a new manual in 2026. It took effect July 1, 2026. Confirm which version applies to your permit with Clark County Community Development.
What counts as hard surface?
Almost anything that sheds rain counts. The manual lists roof tops, walkways, patios, driveways, parking areas, concrete and asphalt. Gravel roads and packed earth count too.
Permeable pavement and green roofs also count toward the total, even though they let water through.
Replaced surfaces count the same as new ones. If you tear out an old driveway and pour a new one, that area is in the total.
What goes in a small-project stormwater plan?
A small project can use the county’s Stormwater Site Plan Short Form. It is Appendix 1-I of Book 1. The county calls a project small when it meets all four of these:
- It triggers only Minimum Requirements 1 to 5.
- It is less than one acre.
- It does not build a public road.
- It does not need an Engineering Approval.
The Short Form asks for these parts:
- A project overview, with the square feet of each new roof, driveway and patio.
- A summary of the site as it is now, and where water enters and leaves.
- A soils assessment.
- A short write-up of how you meet each requirement.
- An erosion and sediment control plan for the building phase.
- Maps, plans and drawings.
You may not need an engineer for this. Clark County Code 40.386.030 exempts some plans from the engineer rule. The exemption covers residential buildings on an existing lot that only need Minimum Requirements 1 to 5.
The erosion control part is its own topic. See who handles erosion control on a building site.
Do I need soil testing?
Every site needs a soil description, and some need testing. The Short Form says the description can come from the county’s published soil maps on Clark County MapsOnline.
Some sites also need an infiltration rate test. That test measures how fast water soaks into your soil. It decides if a rain garden or permeable pavement will work on your lot.
A groundwater check can be required too. It applies when infiltration is planned and the seasonal high groundwater is known to be shallow. The form sets that line at less than five feet below the base of a rain garden or permeable pavement.
The county lets several kinds of people do this work. The list includes a certified septic system designer, a soil scientist and a professional engineer.
Where does the roof and driveway water go?
The goal is to keep it on your lot. Minimum Requirement 5 says to infiltrate, disperse and retain runoff on site as much as is feasible. The county’s short list of tools includes:
- Downspout infiltration. Roof water runs to a drywell or a rock-filled trench and soaks in.
- Downspout dispersion. Roof water spreads out over a planted area.
- Rain gardens. A shallow planted basin that holds water while it soaks in.
- Permeable pavement. A driveway surface that lets water pass through.
- Soil quality and depth. Good, deep soil in the finished yard, so the lawn soaks up rain.
Which tools you can use depends on your soil. Fast-draining soil makes this simple. Clay and high groundwater make it harder.
These drywells, trenches and pipes are part of the residential excavation scope on most new homes. Ask each bidder if the stormwater plan items are in their price. For what you can and cannot do with the water, see where drainage water can go.
What does the City of Vancouver require?
Vancouver uses the same square-foot triggers. The city’s code, VMC 14.25, ties them to the city’s state stormwater permit. The city’s Stormwater and Erosion Control Checklist states them plainly. A construction stormwater plan is required at 2,000 square feet of new plus replaced hard surface. It is also required at 7,000 square feet of land disturbance.
The city’s Surface Water General Requirements add local rules for small residential projects:
- You submit the city’s Stormwater Applicability Form.
- You submit a Stormwater and Erosion Control Site Plan.
- All roof and driveway runoff must be infiltrated on site. The exceptions are poor infiltration, high groundwater, steep slopes and lots with more than three feet of fill.
- Infiltration systems stay at least 10 feet from any building foundation.
- Residential systems stay at least 5 feet from a neighbor’s property line.
- Where soil soaks in less than 2 inches per hour, a Professional Engineer must design the system.
Camas, Washougal, Battle Ground, Ridgefield and La Center each run their own permits. Ask that city for its rules.
What if my project is under the triggers?
You skip the full plan, but not erosion control. The county manual says projects under both triggers do not have to prepare a construction stormwater plan. They still have to control erosion on the site. In Vancouver, small projects still submit the applicability form and a site plan.
Do this now
- Add up the square feet of your planned roof, driveway, walks and patio. Compare the total to 2,000 and 5,000.
- Estimate how much ground will be cleared or graded. Compare it to 7,000 square feet.
- Look up your lot’s soil type on Clark County MapsOnline.
- Ask your permit office which stormwater manual and which form apply to your address.
- Ask each bidder which stormwater plan items are in their price.
More questions
Do I need an engineer for the stormwater plan?
Not always. In unincorporated Clark County, a house on an existing lot that only triggers Minimum Requirements 1 to 5 is exempt from the engineer rule. At 5,000 square feet of hard surface, plan on an engineer.
Does a gravel driveway count as hard surface?
Plan on it. The county’s definition of impervious surface lists gravel roads and packed earthen materials. Ask the county to confirm for your driveway.
Which county manual applies to my project?
The 2026 manual took effect July 1, 2026. The county says the 2021 manual applies to most projects that applied before that date. Ask Community Development to confirm.
Sources
- Clark County: Stormwater Code and Manual, 2026 Clark County Stormwater Manual Book 1 and Appendix 1-I (read November 23, 2026)
- Clark County: Ordinance amending CCC 40.386, Stormwater and Erosion Control, effective July 1, 2026 (read November 23, 2026)
- City of Vancouver: Engineering Stormwater and Erosion Control Checklist (read November 23, 2026)
- City of Vancouver: Surface Water General Requirements, Section 4, February 18, 2025 (read November 23, 2026)
Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.