Short answer
A Washington construction site needs the state Construction Stormwater General Permit when it disturbs one acre or more and stormwater could reach surface water. Smaller sites need it too when they are part of a larger plan that will disturb one acre or more. General contractors and developers must apply at least 60 days before any discharge.
What triggers the permit?
One acre of disturbed ground is the trigger. As of November 2026, the Washington Department of Ecology’s Construction Stormwater General Permit covers clearing, grading and excavation that meets two tests:
- The work disturbs one acre or more.
- Stormwater from the site discharges to surface waters of the state.
Ecology’s permit page puts the second test this way. Is there any possibility that stormwater could run off the site or enter a system that leads to surface water? Ecology says in almost every case there is.
Count all of it. The acre includes staging yards, haul roads, stockpiles and off-site support areas.
One kind of site does not need coverage. That is a site where all stormwater goes into the ground, with no discharge to surface water or a storm sewer.
The current permit took effect January 1, 2026 and expires December 31, 2030. Permits change, so confirm the details with Ecology before you bid.
What is a common plan of development?
It is one plan built in pieces. The permit’s definition covers phased projects and projects with many lots. It still applies when the phases or lots are built by different contractors or owners. The permit gives the example of a development where lots are sold to separate builders.
This is where small sites get caught. If your pad is half an acre inside a 10-acre subdivision, the whole plan sets the rule. The permit says the disturbed area of the entire plan is used to decide what is required.
Ask the developer for the permit number before you price the work. Coverage can also be transferred to a new operator with a Transfer of Coverage form.
How do you apply, and how long does it take?
You apply online and you need at least 60 days. The application is called a Notice of Intent, or NOI. The steps in the permit are:
- Submit the NOI at least 60 days before stormwater will discharge from the work.
- Publish a public notice in a newspaper of general circulation in the county. It runs once a week for two weeks in a row, at least 7 days apart.
- Run the notice after the NOI is submitted.
- Wait out the 30-day public comment period. It starts on the date of the second notice.
Ecology says it tries to issue coverage 45 days after it gets a complete application. For sites with known contamination, Ecology recommends applying 90 to 120 days ahead.
The party who applies is the operator. That is whoever controls the plans, or whoever runs day-to-day work on site.
What is a SWPPP?
A SWPPP is the written plan for keeping mud and pollution on the site. The letters stand for Stormwater Pollution Prevention Plan. The permit says it must have a narrative and drawings. It must cover 13 elements, from marking clearing limits to protecting drain inlets.
The plan has to be in use from the first soil disturbance until final stabilization. It also has to name the site’s CESCL.
One element sets the deadline for covering bare soil. West of the Cascades, soil cannot sit exposed and unworked for more than 2 days from October 1 to April 30. From May 1 to September 30 the limit is 7 days. See excavating in the rainy season for what that does to a winter schedule.
Who inspects, and how often?
A Certified Erosion and Sediment Control Lead, or CESCL, inspects every week. The permit requires that person to:
- Inspect all disturbed areas, controls and discharge points at least once every calendar week.
- Inspect within 24 hours of any discharge from the site.
- Be on site or on call at all times.
Inactive sites that are temporarily stabilized can drop to one inspection each calendar month. Each inspection gets a signed report kept with the site logbook.
Ecology says a CESCL certificate lasts three years from the training date.
When do you have to sample the water?
You sample every week that the site discharges. No discharge that week means no sample. The method depends on the size of the site:
- Under 5 acres disturbed: use a turbidity meter or a transparency tube.
- 5 acres or more: use a turbidity meter.
Turbidity is how cloudy the water is. It is measured in units called NTU. The permit’s benchmark is 25 NTU, or 33 centimeters in a transparency tube.
If a sample is over the benchmark, you have to act:
- At 26 to 249 NTU, fix the controls within 10 days and review the SWPPP within 7 days.
- At 250 NTU or more, report to Ecology within 24 hours. Then sample daily until the water is back to 25 NTU or lower.
Results go to Ecology every month in a Discharge Monitoring Report. A report is due for months with no discharge too.
There is one more test for concrete-heavy jobs. Sites that pour 1,000 cubic yards of concrete or more, or use cement-treated soils, must also sample pH.
How does the state permit fit with city and county rules?
The state permit sits on top of local rules. It does not replace them. You still need local grading and erosion approvals from the City of Vancouver, Clark County or another city.
The two systems do line up. Clark County’s Stormwater Manual says a site can meet the county’s construction stormwater requirement by fully following the state SWPPP. Vancouver’s code, VMC 14.24.060, says much the same.
On a commercial excavation job, the permit holder and the dirt crew are often different companies. Put in the subcontract who provides the CESCL, who samples and who files the monthly reports.
For smaller sites, see who handles erosion control on a building site. Oregon and Portland have their own rules.
Do this now
- Add up every disturbed area on the project, including staging and haul roads. Compare the total to one acre.
- Ask the owner or developer if the site is part of a larger plan that already has permit coverage.
- Count back at least 60 days from your first earthwork date. That is your NOI deadline.
- Name the CESCL in writing and confirm their certificate is current on Ecology’s CESCL list.
- Put sampling, inspections and monthly reports into the subcontract scope.
More questions
Is there a waiver for short summer jobs?
Yes, for some. The Erosivity Waiver is for sites under 5 acres with a low rainfall erosion factor. West of the Cascades, all the work must fall between June 15 and September 15.
When does permit coverage end?
When you file a Notice of Termination after final stabilization. It takes effect on the 31st day after Ecology receives a complete form.
How long do you keep the records?
At least five years after coverage ends. That includes the SWPPP, inspection reports and sampling results.
Sources
- Washington Department of Ecology: 2026 Construction Stormwater General Permit with Errata (read November 23, 2026)
- Washington Department of Ecology: Construction Stormwater General Permit page (read November 23, 2026)
- Washington Department of Ecology: Certified Erosion and Sediment Control Lead (read November 23, 2026)
- Clark County: Stormwater Code and Manual, 2026 Clark County Stormwater Manual Book 1 (read November 23, 2026)
Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.