Short answer
Yes. In Vancouver, city code says all construction in the public right-of-way needs a permit unless it is exempt. That covers a sewer or water tap, a driveway approach, a sidewalk and a utility trench. The contractor must be on the city’s authorized list. County roads use a separate Clark County permit.
What counts as the right-of-way?
It is the public strip that holds the street, and it is usually wider than the pavement. The curb, the sidewalk and the driveway approach are often inside it. The driveway approach is the sloped part of a driveway between the street and your property line.
As of November 2026, Vancouver Municipal Code 11.90.020 says all construction activities in the right-of-way need a permit unless exempt. It names these kinds of work:
- Cutting, opening or digging in a street, alley, sidewalk or curb
- Building, changing or repairing a street, alley, sidewalk, curb or driveway
- Utility work in city-held easements
If you are not sure where the right-of-way ends, ask the city before you dig. Codes change too, so confirm your project with the Permit Center’s Engineering Services.
Which jobs need a Vancouver right-of-way permit?
Any job that cuts into or changes the public street area. The city’s request form lists these common types:
- A water or sewer connection or repair
- A driveway approach or sidewalk for a new home
- Replacing a driveway approach, even at the same size
- Widening or moving an approach, or adding a second one
- Sidewalk repair
- Electrical work
A like-for-like driveway replacement shows how this works. The city says you do not need a land use permit for that. But any part of the work in the right-of-way still needs the right-of-way permit.
City code exempts a few things. One is utility work above ground that does not disturb the surface. Another is routine care of plants, not counting street trees. Work done under a contract with the city is also exempt.
A fence, retaining wall or planter that sits in the right-of-way is a different case. The city handles those under a Street Use Permit.
Who can pull the permit?
In Vancouver, a contractor on the city’s authorized contractor list. The city says contractors must be on that list to get a right-of-way permit. The list is posted on the Engineering Services page and updated monthly.
That means a homeowner usually cannot pull this permit alone. City code has one narrow exception for a homeowner who repairs a sidewalk in person. It applies only when all of these are true:
- The work is sidewalk only, with no driveway approach.
- It is 100 lineal feet of sidewalk or less.
- The street is not a city arterial.
- No hired contractor helps.
For anything else, hire a listed contractor. Ask the contractor to show you where the company appears on the list. Then ask who pulls the permit, and get the answer in the bid.
What does the city ask of the contractor?
Insurance, a bond, notice and inspections. These come from VMC Chapter 11.90.
- Insurance. The standard is $1 million per person, $2 million per accident, and $1 million for property damage. The city must be named on the policy.
- Bond. A surety bond for one and a half times the estimated cost of the work. A bond is a promise, backed by a bonding company, that the work gets finished right.
- Notice. The city’s inspection office must be told at least 48 hours before work starts. The same 48 hours applies before any concrete or asphalt paving.
- Inspection. The work is not complete until the city inspector accepts it.
- Time limit. The permit expires if work has not started within 90 days.
The city’s form must be sent in at least 24 hours before the permit can be issued. Fees are set in the city’s engineering fee schedule. Ask the Permit Center for the current amount.
Do I need a traffic control plan?
Most likely, yes. A traffic control plan is a drawing that shows the signs, cones and flaggers that will guide traffic around the work.
The city says these plans are required for most projects in the public right-of-way. Here is how the city’s street use page sorts them:
- For a sidewalk, shoulder or single-lane closure, the plan is issued with the right-of-way permit.
- For work that affects an intersection, or 3 or more lanes, the contractor works with the city’s traffic engineers.
- There is no charge for the city to review and approve the plan.
Who fixes the pavement, and can a new street be cut?
The contractor restores the street, and a fresh street may be off limits. The bond in city code requires the contractor to put openings in the street back in good and safe condition. It also covers upkeep of the patch for 24 months.
New pavement gets extra protection. VMC 11.80.100 puts a street cut prohibition in place for 5 years after a street is built, rebuilt or resurfaced. The city can allow a cut if there is no better way to bring in the service. It can also set tougher repair rules.
So ask early if your street was paved in the last 5 years. The city expects boring under the road to be looked at before it allows a cut.
What if my road is a county road or in another city?
Then a different office issues the permit. Vancouver’s rules stop at the city limits.
In unincorporated Clark County, county code 12.20A.070 requires a written permit to install, move or repair a utility line in the road right-of-way. That includes private lines. Three things stand out:
- The utility applies for the permit. The code says contractors may not start or renew one.
- A contractor doing the work must be licensed and bonded.
- A traffic control plan is needed if work or equipment will be within 2 feet of the traveled way.
For a sewer hookup, the Clark Regional Wastewater District lists the right-of-way permit in its fee quote when a new lateral is needed. See who connects a house to sewer in Clark County.
Clark County Public Works also runs traffic control permits. It asks for the form at least 10 working days before a lane closure. A full road closure takes eight weeks of notice.
Camas, Washougal, Battle Ground, Ridgefield and La Center each run their own permits. Call that city’s public works office.
Street work is one piece of underground utility work. A right-of-way permit does not replace an 811 request. Read what 811 marks and what it skips before anyone digs.
Do this now
- Find out who owns your road. Ask if it is a City of Vancouver street, a county road or another city’s street.
- Call that office and describe the work. Ask which permits it needs.
- In Vancouver, check that your contractor is on the authorized contractor list.
- Ask if your street was paved in the last 5 years.
- Get a bid that names who pulls the permit, who handles traffic control and who restores the pavement.
More questions
Can I replace my own driveway approach in Vancouver?
Not on your own permit. The city says the right-of-way permit must go to a licensed contractor approved to work in the city right-of-way.
How long is a Vancouver right-of-way permit good for?
It expires if the work has not begun within 90 days. The city may grant one 90-day extension for work that has not started.
Is an emergency repair different?
Yes. City code allows emergency work without a permit first. The city must be told within 24 hours, and a permit must follow.
Do Portland rules apply here?
No. Oregon and Portland have their own rules.
Sources
- Vancouver Municipal Code: Chapter 11.90, Construction in Right of Way (read November 23, 2026)
- City of Vancouver: Engineering Services, Right-of-Way Permit (read November 23, 2026)
- City of Vancouver: Street Use Permits and Traffic Control Plan (read November 23, 2026)
- Clark County Code: Chapter 12.20A, Accommodation of Utilities on County Road Right-of-Way (read November 23, 2026)
Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.