Before You Dig · Grading permits

Vancouver or Clark County: Whose Grading Rules Apply?

Updated For homeowners, builders and general contractors5 minute read

Short answer

The rules follow the parcel, not the mailing address. Look up the property in Clark County’s Property Information Center and read the Jurisdiction line. In unincorporated Clark County, a grading permit starts at more than 50, 100 or 200 cubic yards. The number depends on lot size and urban or rural zoning. The city’s general trigger is 10.

How do I check which jurisdiction my lot is in?

Look up the parcel on the county’s map site. The City of Vancouver says it plainly on its Property Information Lookup page: not all postal addresses with “Vancouver, WA” are inside Vancouver city limits.

Here is the city’s method:

  • Open the Clark County Property Information Center.
  • Search by street address or tax account number. The tax account is also called the parcel number.
  • Under “Administrative Data,” find “Jurisdiction.”

If it says Vancouver, city rules apply. If it says Clark County, county rules apply. If it names another city, call that city.

When does unincorporated Clark County require a grading permit?

It depends on three things: urban or rural, lot size, and how much earth you move. As of November 2026, Clark County Code Chapter 14.07 requires a grading permit when grading involves:

  • More than 50 cubic yards, in urban areas on sites under one acre.
  • More than 100 cubic yards, in urban areas on sites of one acre or more.
  • More than 100 cubic yards, in rural areas on sites under five acres.
  • More than 200 cubic yards, in rural areas on sites of five acres or more.
  • More than 50 cubic yards inside a critical area, urban or rural.

Critical areas are flood hazard areas, geologic hazard areas, wetlands and habitat areas. Shoreline areas count too.

The county calls this a grading and drainage permit. It is one permit that covers earthwork, erosion control and drainage. Codes change, so confirm with Clark County Development Engineering before you dig.

How does the county count the cubic yards?

The county adds two numbers. The first is all the soil you dig out on site. The second is all the fill you haul in from somewhere else.

Jobs on one site also add up. The code says all grading on a site is viewed together, except grading covered by an earlier permit. Two small jobs can cross the line as one.

Being under the number does not always get you out. The county’s Grading and Drainage Review handout says a permit is still required if the project triggers stormwater rules.

What grading is exempt in the county?

The code lists the exemptions. The ones most people ask about are:

  • Excavation to build a structure that already has a county permit.
  • Excavations for wells, and trenches for utilities.
  • Ordinary farming work, such as tilling and soil preparation.
  • Road and driveway upkeep, such as pothole patching, shoulder grading and resurfacing with the same material.

Read the first one closely. It covers the dig for a structure that is permitted. It does not cover grading a lot before the house permit exists. See can I clear and grade before my building permit.

An exemption from the permit is not a pass on the rest of the code. Erosion control and critical area rules still apply.

Is my county lot urban or rural?

Your zoning decides it. The county handout says to find the zoning in the Property Information Center. Then check the table in Clark County Code Section 40.200.010. It lists each zoning district as urban or rural.

This matters because the permit numbers change. A rural lot under five acres gets 100 cubic yards. An urban lot under one acre gets 50.

How is the City of Vancouver different?

The city starts much lower. Its Grading Projects FAQ says a permit is required for nearly all projects that move more than 10 cubic yards.

A few more differences:

  • In the city, a house foundation dig can skip the separate grading permit only at 50 cubic yards or less. Six other conditions must be met too.
  • In the county, digging for a permitted structure is exempt with no volume limit in the grading chapter.
  • In the county, grading over 5,000 cubic yards must be designed by a licensed engineer or geologist. So must any fill that will support a structure.

The full city rules are in do I need a grading permit in Vancouver, WA.

What if the lot is in Camas, Washougal, Battle Ground, Ridgefield or La Center?

Then neither set of numbers above applies. Each of those cities runs its own permits. The Jurisdiction line will name the city. Call that city’s permit office and ask for its grading permit rules.

Oregon and Portland have their own rules too.

If you are getting bids for site prep and grading, put the jurisdiction on the first page of your plans. Ask each bidder who pulls the grading permit, and get the answer in the bid.

Do this now

  1. Search your address in the Clark County Property Information Center and write down the Jurisdiction and the zoning.
  2. Write down the lot size in acres from the same page.
  3. Add up your cut on site plus any fill you will haul in. Divide cubic feet by 27 to get cubic yards.
  4. Compare your total to the right number: the city’s 10, or the county’s 50, 100 or 200.
  5. Call the permit office for that jurisdiction and confirm before you move soil.

More questions

Does a county grading permit expire?

Yes. The county code says the grading plan approval expires one year from the approval date unless construction starts first. A one year extension can be requested if the fee is paid before it expires.

Do I need an engineer for a county grading permit?

Not always. Under 5,000 cubic yards, the code allows “Regular Grading” without a registered design professional. Fill that supports a structure always needs an engineered application.

Does a simpler county permit exist for small rural jobs?

Yes. Grading-only projects under 500 cubic yards in the rural area, away from critical areas, may qualify for a simplified grading permit. The code lists eight conditions.

Sources

Written by Lindberg Pipe & Grade, an excavation contractor in Vancouver, WA since 2008, from the agency pages and codes listed above. Rules and fees change. This is general information, not legal or engineering advice, so check with the permit office for your address before work starts.